PARRAMATTA PROJECT A CONSTRUCTION POWERHOUSE FOR NSW BUSINESS
28th Feb 2023
The project’s largest concrete slab has been poured and the first of 12,000 tonnes of structural steel has been installed in a major milestone for the construction of Powerhouse Parramatta.
READ MORE
-
COMMUNITY CONSTRUCTION NOTICE
25th Jan 2023
Out of hour steel deliveries will arrive to site over the year from approximately 30 January 2023.
READ MORE
-
Construction site closure – December/January holiday period
14th Dec 2022
The Powerhouse Parramatta construction site will be closed for the December/January holiday period from Friday 23 December 2022 and re-open Wednesday 4 January 2023.
READ MORE
-
COMMUNITY CONSTRUCTION NOTICE
7th Dec 2022
Tower crane 3 is scheduled to be established in two stages from Monday 12 December 2022 to Saturday 7 January 2023.
READ MORE
-
COMMUNITY CONSTRUCTION NOTICE
2nd Dec 2022
Night works to install and commission new pipework required to supply water to the project site is scheduled from 12 to 16 December.
READ MORE
-
Renewable diesel powers construction
21st Nov 2022
In an Australian first, Powerhouse Parramatta and the New Sydney Fish Market are using 100% renewable diesel in their tower cranes, enabling fossil free construction.
READ MORE
-
COMMUNITY CONSTRUCTION NOTICE 7th Nov 2022
7th Nov 2022
Tower crane 2 will be established from 14 November to assist with the movement of heavy materials on site.
READ MORE
-
OCTOBER 2022 CONSTRUCTION UPDATE
7th Oct 2022
Our October community construction update will keep you informed of progress onsite and showcase any key milestones reached in delivering this important project for Western Sydney.
READ MORE
-
ELECTRICAL MAINTENANCE WORKS
2nd Sep 2022
Endeavour Energy will be carrying out essential maintenance between 10 and 11 September and power supply will be interrupted.
READ MORE
-
COMMUNITY CONSTRUCTION NOTICE
26th Aug 2022
Tower crane 1 will be established from 1 September. Three free standing tower cranes will be installed on site to assist with the movement of heavy materials on site.
READ MORE
-
COMMUNITY CONSTRUCTION NOTICE
16th Aug 2022
Piling equipment will be demobilised over two separate occasions via George Khattar Lane.
READ MORE
-
Community Construction Notice - July 2022
20th Jul 2022
Out of hours works are taking place as part of ongoing high voltage infrastructure works at the intersection of Phillip Street and Dirrabarri Lane.
READ MORE
-
A new temporary footpath on George Khattar Lane
13th Jul 2022
A new temporary footpath is being installed from the riverfront pathway to the existing pathway on George Khattar Lane.
READ MORE
-
JUNE 2022 CONSTRUCTION UPDATE
24th Jun 2022
Welcome to our June construction update to keep you informed of progress onsite and showcase any key milestones reached in delivering this important project for Western Sydney.
READ MORE
-
MAY 2022 CONSTRUCTION UPDATE
19th May 2022
Welcome to our first monthly construction update to keep you informed of progress onsite and showcase any key milestones reached in delivering this important project for Western Sydney.
READ MORE
-
COMMUNITY CONSTRUCTION NOTICE
10th May 2022
Stormwater services diversions are taking place on the western side of Wilde Avenue at the intersection of Phillip Street.
READ MORE
-
Electrical upgrades works
30th Apr 2022
Fredon will be completing electrical upgrade night works on Phillip Street between 2 and 13 May.
READ MORE
-
Construction site closure – Easter holiday period
14th Apr 2022
The Powerhouse Parramatta construction site will be closed for the Easter break from Friday 15 April and re-open Wednesday 20 April.
READ MORE
-
Powerhouse Exoskeleton exhibition now showing at WSU
7th Apr 2022
Now showing at Western Sydney University's Engineering Innovation Hub, the Exoskeleton exhibition explores the development of the concept, detailed design and prototyping of the steel lattice exoskeleton.
READ MORE
-
Community construction notice
29th Mar 2022
Piling activity will commence in late March 2022 and take approximately four months to complete.
READ MORE
-
Powerhouse Parramatta – this year’s flood peaks
18th Mar 2022
The highest recent river levels were recorded on 22 February and 8 March 2022 where the levels were at circa RL3.5, which is about 1.6 metres above the concrete River edge (RL1.9).
READ MORE
-
POWERHOUSE PARRAMATTA – HEAVY RAIN EVENT ON 22 FEBRUARY 2022
23rd Feb 2022
Water from the heavy rain event on Tuesday 22 February would have peaked around 4 metres below the future Powerhouse Parramatta ground floor.
READ MORE
-
Community construction notice
8th Feb 2022
Lendlease are now responsible for managing the Powerhouse Parramatta site and outline some pedestrian access changes, construction hours and the site location and boundary.
READ MORE
-
WILLOW GROVE COMMUNITY REFERENCE GROUP – NOMINATIONS OPEN
18th Oct 2021
Create Infrastructure is establishing the Willow Grove Community Reference Group (WG-CRG) to work in partnership with the community and stakeholder groups to ensure the successful relocation and reuse of Willow Grove house.
READ MORE
-
POWERHOUSE PARRAMATTA APPOINTS CONSTRUCTION PARTNER
17th Sep 2021
Powerhouse Parramatta has reached a major milestone with the main works contract awarded to deliver the world-class cultural icon in the geographical heart of Sydney.
READ MORE
-
Construction has restarted on the Powerhouse Parramatta Project
11th Aug 2021
In line with the NSW Government’s COVID-19 Guidelines, construction on the Powerhouse Parramatta resumed on Wednesday 11 August 2021.
READ MORE
-
Construction pause
19th Jul 2021
As a result of the NSW Government’s COVID-19 restrictions announced over the weekend, work on the Powerhouse Parramatta has now temporarily paused.
READ MORE
-
Celebrating 6 months in the Powerhouse Community Space
30th Jun 2021
Since opening in December 2020, over 2,000 people have visited the Powerhouse Community Space to learn more about the project, the Powerhouse Museum and its iconic collection.
READ MORE
-
June 2021 project update
21st Jun 2021
Ancillary works have started. This includes the careful dismantling of Willow Grove. This work will follow the approved Relocation Framework and will be overseen by a heritage specialist to ensure Willow Grove is carefully dismantled and safely stored.
READ MORE
-
MAY 2021 PROJECT UPDATE
18th May 2021
Following planning approval in 2021, early works are well underway on the Powerhouse Parramatta site.
READ MORE
-
WESTERN SYDNEY UNIVERSITY STUDENTS TO GET HANDS-ON IN DELIVERY OF POWERHOUSE PARRAMATTA
28th Apr 2021
Western Sydney University students will have the opportunity to play a role in the delivery of NSW’s newest Cultural Institution – the Powerhouse Parramatta.
READ MORE
-
Update on 20 March 2021 heavy rain event
21st Mar 2021
Water from the heavy rain event on Saturday 20 March wouldn’t have come within four metres of the future Museum’s ground floor.
READ MORE
-
Local access changes
15th Feb 2021
As part of the construction of the new Powerhouse Parramatta, a number of access changes around the site are necessary.
READ MORE
-
Planning approval granted for Powerhouse Parramatta
15th Feb 2021
On 11 February 2021, the Department of Planning, Industry and Environment approved the State Significant Development Application for Powerhouse Parramatta.
READ MORE
-
December 2020 project update
31st Dec 2020
The Powerhouse Community Space is now open in Parramatta Square. Visit maas.museum/parramattasquare for opening hours and more information.
READ MORE
-
October 2020 project update
31st Oct 2020
Infrastructure NSW has now reviewed all 1,300 submissions received during the exhibition of the State Significant Development Application. A Response to Submissions Report has been prepared to address the matters raised.
READ MORE
-
July 2020 project update
31st Jul 2020
The exhibition period for the Environmental Impact Statement (EIS) has now closed. Infrastructure NSW will now consider all submissions received during the EIS exhibition period and respond to the matters raised in a Response to Submissions Report.
READ MORE
-
June 2020 project update
30th Jun 2020
An Environmental Impact Statement (EIS) has been developed as part of the State Significant Development Application for the new Powerhouse in Parramatta.
READ MORE